The installation is complete.
Installing the secondary riser board
Prerequisites
Before you perform this procedure, make sure that you have the following items available:
•
T-10 Torx screwdriver
•
T-15 Torx screwdriver
Procedure
1.
Power down the server.
2.
Disconnect all peripheral cables from the server.
3.
Remove the server.
4.
Place the server on a flat, level work surface.
5.
Remove the node cover.
6.
Remove the air baffle.
7.
Remove the riser cage screws (callout 1), and then lift the riser cage off the system board (callout 2).
There is a hole on the front end of the riser cage for finger access in pulling up the riser.
Hardware options installation