12. Connect each power cord to the power source.
13. Power up the server (Powering up the server on page 24).

Installing an expansion board in the secondary riser cage

Prerequisites
Before installing this option, be sure that you have the following:
The components included with the hardware option kit
Procedure
1.
Observe the following alerts:
WARNING:
To reduce the risk of personal injury from hot surfaces, allow the drives and the internal system
components to cool before touching them.
CAUTION:
To prevent damage to electrical components, properly ground the server before beginning any
installation procedure. Improper grounding can cause electrostatic discharge.
2.
Back up all server data.
3.
Power down the server (Power down the server on page 24).
4.
Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
5.
Do one of the following:
a. Extend the server from the rack (Extend the server from the rack on page 24).
b. Remove the server from the rack (Remove the server from the rack on page 25).
6.
Remove the access panel (Remove the access panel on page 25).
7.
Install a secondary riser cage:
Low-profile (Installing a secondary low-profile PCIe slot riser cage option on page 76)
Full-height (Installing a secondary full-height PCI riser cage option on page 74)
8.
Remove the expansion slot blank:
Half-length
78