SET-UP AND INSTALLATION
b. If using both the 10.1 m (33 feet) and 7 m (23 ft)
sections, use the controller to pivot jib towards
boom such that the lugs on the 7 m (23 ft) section
align with rear stowage bracket.
6642-38
NOTE:
Perform steps 14 and 15 if stowing the 10.1 m (33
ft) section when the 7 m (23 ft) section remained on
the boom, otherwise proceed to step 19.
14. If the bi-fold 7m (23 ft) section was not used, remove pin
(1, Figure 4-50, photo 6642-9) from the base section
locking bar (2). Move locking bar (3, Figure 4-50, photo
6642-8) to the 7 m (23 ft) section (4) and install pin (1).
Secure with retaining pin.
1
2
6642-9
15. If the bi-fold 7m (23 ft) section was not used, remove bi-
fold stowage pin (1, Figure 4-51) from bi-fold and install
at the lattice/bi-fold connection. Install retainer clip to pin.
22
1
2
FIGURE 4-49
4
1
3
6642-8
FIGURE 4-50
Published 02-06-2014, Control # 495-00
TMS800E13 OPERATOR MANUAL
6642-41
NOTE:
Step 16 applies when the 7m (23 ft) section was
erected with the 10.1 m (33 ft) section.
16. Install rear stowage pin (1, Figure 4-52) and retainer clip
(2).
6642-39
17. Lower boom.
18. Remove tag line.
Reeve the hoist cable as described in this section
Raising and Lowering the Hydraulic Jib
NOTE:
For more information on operation of the jib
s w i t c h e s , r e f e r t o O p e r a t i n g C o n t r o l s a n d
Procedures, page 3-1.
When Erecting
To remotely raise or lower the lattice extension when
erecting there are two control units each with two push
buttons on the 10.1 m (33 ft) section.
1
FIGURE 4-51
1
2
FIGURE 4-52