Weekly And Monthly Inspections - Brainlab CURVE DUAL System User's Manual

Hide thumbs Also See for CURVE DUAL:
Table of Contents

Advertisement

SYSTEM OVERVIEW
2.5.3

Weekly and Monthly Inspections

Authorization
Only qualified clinical personnel are authorized to perform weekly and monthly inspections.
Weekly Inspections
Component
Cabling
Charge battery of UPS
Monthly
Inspections
Component
UPS
Monitor and camera
arms
Camera arm
Labeling
Wheels and brakes
Every Three
Months
Component
UPS
System User Guide Rev. 1.0 Curve Dual Display, Curve Single Display Ver. 1.0
Inspection
Visual control (twists, cracks).
The UPS battery charges whenever it is connected to utility power
and typically requires less than 5 hours to charge fully.
Inspection
Turn the Curve system on (see page 89). Utility power is supplied to
the system.
Perform a simulated utility blackout test to confirm that the UPS unit
can switch from utility power to battery power and back again, without
affecting the equipment powered by UPS. System must still be "On".
Functionality and visual control (wear and tear).
Functionality
Legibility
Functionality
Inspection
• Discharge the battery by unplugging the mains power from the wall
• Wait until the system shuts down (max. five minutes).
• Plug in mains power and turn system on again.
• Repeat this process until the system shuts down immediately after
• Fully charge battery by plugging in the system and switching on the
To optimize battery lifetime of the UPS it is recommended to fully discharge the battery
once every three months.
outlet while the system is running.
unplugging mains power and system emits a long beep followed by
short beeps. The battery is now empty.
mains power switch for two or more hours.