Operating Instructions
Single-pole conductor-rail system
SingleFlexLine Program 0815
7.2.2
Initial start-up of the conductor-rail system
1.
Every time before the machine/system is started, measure the insulation resistance of the conductor-rail system according to
locally applicable technical standards, directives and legal regulations.
2.
Carry out locally required electrical tests.
3.
Perform a complete run along the conductor-rail (walking pace).
Remark: Insulation resistance test according to EN 60204-1: 2006 ≥ 1 MΩ at a measuring voltage of 500 VDC. Exception for
busbars, conductor-rails and slip rings ≥ 50 kΩ (EN 60204-1/18.3: 2006)
The current collectors must not become caught, stick or scrape!
→ Where necessary, repair any faults and perform setting tasks.
ATTENTION!
4.
Visual inspection of the device/system:
Current collector undamaged and without signs of heavy wear
→
Conductor-rail components undamaged and in the proper location. No displacements or distortions. Check hanger clamps,
→
end caps and fixed points in particular!
Check that there are no visible signs of heavy wear (chips, plastic parts, etc.). Signs of heavy wear indicate that installation
→
clearances and their tolerances are not complied with. This can sometimes also be the case for individual sections of the route.
BAL0815-0002d-US
www.conductix.us
translated document
page 67 of 94
Need help?
Do you have a question about the SingleFlexLine Program 0815 and is the answer not in the manual?
Questions and answers