Initial Start-Up Of The Conductor-Rail System - Conductix-Wampfler SingleFlexLine Program 0815 Operating Instructions Manual

Single-pole conductor-rail system
Hide thumbs Also See for SingleFlexLine Program 0815:
Table of Contents

Advertisement

Operating Instructions
Single-pole conductor-rail system
SingleFlexLine Program 0815
7.2.2

Initial start-up of the conductor-rail system

1.
Every time before the machine/system is started, measure the insulation resistance of the conductor-rail system according to
locally applicable technical standards, directives and legal regulations.
2.
Carry out locally required electrical tests.
3.
Perform a complete run along the conductor-rail (walking pace).
Remark: Insulation resistance test according to EN 60204-1: 2006 ≥ 1 MΩ at a measuring voltage of 500 VDC. Exception for
busbars, conductor-rails and slip rings ≥ 50 kΩ (EN 60204-1/18.3: 2006)
The current collectors must not become caught, stick or scrape!
→ Where necessary, repair any faults and perform setting tasks.
ATTENTION!
4.
Visual inspection of the device/system:
Current collector undamaged and without signs of heavy wear
Conductor-rail components undamaged and in the proper location. No displacements or distortions. Check hanger clamps,
end caps and fixed points in particular!
Check that there are no visible signs of heavy wear (chips, plastic parts, etc.). Signs of heavy wear indicate that installation
clearances and their tolerances are not complied with. This can sometimes also be the case for individual sections of the route.
BAL0815-0002d-US
www.conductix.us
translated document
page 67 of 94

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SingleFlexLine Program 0815 and is the answer not in the manual?

Questions and answers

Table of Contents