2.7 First commissioning vector control AC drive blocksize format

2.7
First commissioning vector control AC drive blocksize format
An example provided in this chapter explains all the configuration and parameter settings, as
well as tests that are required for initial commissioning. Commissioning is carried out using
the STARTER commissioning tool.
Preconditions for commissioning
● The commissioning preconditions (Page 18) have been met.
● The commissioning checklists (Page 20) (Tables 1-1 and 1-2) have been completed and
● The STARTER commissioning tool is installed and activated.
● The drive system has been wired according to the specifications.
● The communication between the PG/PC and drive system has been prepared.
● The power supply of the Control Unit (24 V DC) has been switched on.
2.7.1

Task

A drive unit is to be commissioned (vector control, closed-loop speed control), without
DRIVE-CLiQ and without speed encoder with the following components:
Designation
Closed-loop control
Control Unit
Operator Panel
Infeed and drive
Power Module
Motor
Commissioning is performed using the BOP20.
The function keys on the BOP20 must be parameterized so that the ON/OFF signal and
speed settings can be defined via these keys.
122
the points fulfilled.
– see the "Readme" file on the STARTER installation DVD
Component
Control Unit 310-2 DP
Basic Operator Panel BOP20
Power Module 340
Induction motor
(without DRIVE-CLiQ interface)
Order number
6SL3040-1LA00-0AA0
6SL3055-0AA00-4BAx
6SL3210-1SB14-xxxx
1LA7
Commissioning Manual, (IH1), 01/2013, 6SL3097-4AF00-0BP3