Chapter 31. Layer 2 Failover

© Copyright Lenovo 2018
The primary application for Layer 2 Failover is to support Network Adapter 
Teaming. With Network Adapter Teaming, all the NICs on each server share the 
same IP address, and are configured into a team. One NIC is the primary link, and 
the other is a standby link.For more details, refer to the documentation for your 
Ethernet adapter. 
Note: Only two links per server blade can be used for Layer 2 LAG Failover (one 
primary and one backup). Network Adapter Teaming allows only one backup NIC 
for each server blade.