66
Hardware installation procedures
Connecting the power cords to the hardware
Connecting the power cords to the hardware
A
B
A
B
A
B
11
Refer to the following section to turn on all devices in the proper order. It is
very important to turn on the devices in the correct sequence; second Expansion
Shelf, initial Expansion Shelf, Primary Shelf, compute node.
See "Turning on the hardware and verifying operation" on page 68.
12
When all devices are operational, add the storage disk space to the appliance
system.
See "Adding the disk space of a new Expansion Storage Shelf" on page 81.
Each compute node and each storage shelf contain two AC power supplies. To
ensure power redundancy, connect the power supplies on each component to
different AC power sources.