VERITAS NetBackup 5330 Appliance Hardware Installation Manual page 69

Storage shelves and disk drives
Hide thumbs Also See for NetBackup 5330:
Table of Contents

Advertisement

Fiber Channel (FC) cables between the compute node and the Primary
Shelf
SAS cables between the Primary Shelf and the Expansion Shelf
Power cords from each component to the appropriate Power Distribution
Unit (PDU) in the rack
2
On the rear of the Expansion Shelf, turn on both power switches.
3
Verify that the left-most LEDs on both power canisters are green.
Hardware installation procedures
Turning on the hardware and verifying operation
69