Fiber Channel (FC) cables between the compute node and the Primary
■
Shelf
SAS cables between the Primary Shelf and the Expansion Shelf
■
Power cords from each component to the appropriate Power Distribution
■
Unit (PDU) in the rack
2
On the rear of the Expansion Shelf, turn on both power switches.
3
Verify that the left-most LEDs on both power canisters are green.
Hardware installation procedures
Turning on the hardware and verifying operation
69