Connecting a second Expansion Shelf to an existing 3TB Expansion Shelf and a 3TB Primary Shelf

Connecting a second Expansion Shelf to an
existing 3TB Expansion Shelf and a 3TB Primary
Shelf
A soft shutdown informs the NetBackup Appliance operating system to stop and
close all active processes. A soft shutdown also stops all communications to the
attached storage shelf. After the operating system stops all of the processes, the
compute node powers itself off. All attached storage shelves should be turned off
with the power switches on the rear panel of each shelf.
Note: When you add one Expansion Shelf to an existing compute node and a
Primary Shelf, you do not have to turn off the power.
To perform a soft shutdown
1
Ensure that all backup or restore operations have been completed.
2
Log in to the NetBackup Appliance Shell Menu and issue the command,
Support > Shutdown.
You can add one Expansion Shelf that uses 6TB disk drives to an existing appliance
system that has 3TB disk drives.
Note: Before you add a second Expansion Shelf to your system, you must upgrade
to NetBackup Appliance Release 2.7.1, or later. Refer to the NetBackup Appliance
Upgrade Guide for Release 2.7.x - RedHat Enterprise Linux (RHEL) Operating
System, which is located at the following site.
https://veritas.com/support/en_US/article.DOC2792.html
Caution: When you add a second Expansion Shelf to an operational appliance
system, best practices recommend that you turn off the compute node, the Primary
Shelf, and the existing Expansion Shelf.
However, it is possible to add an Expansion Shelf to a functioning system while the
power remains on. If you need to keep the power on, contact Technical Support
for assistance. Ask your representative to reference Article 000097607.
Turn off the compute node, the Primary Shelf, and the existing Expansion Shelf in
that order. Refer to the following link for background information as needed.
See "Performing a soft shutdown before adding a new Expansion Shelf" on page 54.