Section 3A
Abnormal Procedures
Depending on the cause of the Bus Over-
load condition, battery operating time on
the affected side may be less than 30 min-
utes. When power to the Left Bus is only
being supplied by the battery, be prepared
to use standby instruments.
5. Land at the nearest suitable airport.
SURFACE DEICE AIR PUMP [L AIR PUMP] or [R AIR
PUMP]
1. Surface Deice Boots . . . . . . . . . . .CHECK OPERATION
2. Deice pressure gage:
a. While boots are inflating . . . . . . . . . . . . . . 9 to 20 PSI
b. When boots are fully inflated . . . . . 15 PSI MINIMUM
If boots operate normally:
3. Operations in icing conditions at pilot's discretion; avoid,
if possible.
Otherwise:
4. Do not enter or continue operations in icing conditions.
3A-26
Model G58