a. Loosen the screws that secure the brackets to the chassis.
See
FIGURE 5-8
b. Raise the brackets all the way.
c. Tighten the screws to secure the brackets to the chassis.
▼ To Roll Out the Chassis
1. Ensure that the floor space up to 5 feet (1.5 m) from the end of the ramp is clear.
2. Prepare the personnel.
One person (pusher) will push the chassis off the pallet from the end opposite
■
the ramps.
One person (guider) at the left of the chassis (left side of ramps) will guide the
■
chassis off the pallet and brake its roll down the ramps.
One person (guider) at the right of the chassis (right side of ramps) will guide
■
the chassis off the pallet and brake its roll down the ramps.
See
FIGURE 5-9
.
.
Chapter 5
Unpacking the Chassis
31