fourth panel can be laid in front of the chassis in the direction of travel. Once the
chassis has rolled off the rear-most panel, lift that panel and move it to the front.
Repeat this process down the path over carpeting.

Grades

The Sun Datacenter Switch 3456 chassis weighs 1433 pounds (650 kg) as shipped.
Any grade along the path requires additional effort to move the chassis, or prevent
the chassis from moving. Do not attempt to move the chassis up or down a grade
greater than 3%.
Additionally, the Sun Datacenter Switch 3456 chassis is equipped with antitilt bars
that are mounted at the centerline. The presence of the bars limits the clearance
movement to 0.5 inch (12 mm). When a chassis peaks a grade of 3% or greater, the
antitilt bars bottom out.

Elevators

If the path to the final location requires use of an elevator, ensure that the elevator
can safely accommodate the weight of the Sun Datacenter Switch 3456 chassis and
the personnel moving it.
The elevator doors must be wide enough to allow the Sun Datacenter Switch 3456 to
pass, ideally with personnel alongside. The doors might need to be held open, either
physically, or by pressing the door open button within the elevator.
Verify that the threshold at the elevator doors permits the chassis to enter and exit
the elevator. The gap between the floor and elevator should not be too large, nor
should there be any height difference. Check this gap at both the entering and
exiting floors. If there are any minor discrepancies, a metal sheet or masonite panel
can be used to compensate.

Doors

Doors must open wide enough to accommodate the Sun Datacenter Switch 3456
chassis and personnel alongside. Additional personnel can hold doors open, or the
doors can be securely propped open using wedges or catches. Do not hold doors
open with chairs or other easily available objects. Such objects do not guarantee a
secure door and can diminish the space for moving the chassis.
16
Sun Datacenter Switch 3456 Installation Guide • December 2008

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Datacenter Switch 3456 and is the answer not in the manual?

Table of Contents