Receiving Area

This section lists the equipment used in the receiving area or loading dock and the
condition and state of the area.

Equipment

To receive and unpack the Sun Datacenter Switch 3456, the following equipment is
required.
Forklift or pallet jack rated for at least 2000 lbs
Large flat-blade screwdrivers (one for each person unpacking)
Claw hammer (one for each person unpacking)
Adjustable wrench (two for each person unpacking)
Scissors
Gloves (for each person unpacking)
Bin for parts collection

Cleanliness

The unpacking area must be clean and uncluttered. Personnel will be working
closely and activity. The personnel must be free to move about without distraction or
the possibility of tripping or slipping.
The task of unpacking produces packing material waste and wood shavings. This
debris should be removed and swept away before the chassis is rolled out.
After rollout, the crate can be reassembled and stored. The unpacking area should be
swept again.

Personnel

This section describes the personnel needed for the installation, what their tasks are,
and their mindset.
18
Sun Datacenter Switch 3456 Installation Guide • December 2008

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Datacenter Switch 3456 and is the answer not in the manual?

Table of Contents