Replacement
Note: Install rails in the frame if not already installed.
1. Position the lift tool such that the new IBF can be moved onto the lift plate.
2. Install the wheel chocks and engage the brake.
3. Move the new IBF onto the tool with the rear side toward the two holes of the lift plate. The side with
the handles is considered the front side.
Note: Ensure the IBF is in the center of the lift plate.
Remove the wheel chocks and disengage the brake.
4. Position the lift tool as close as possible to the rack. Install the wheel chocks and engage the brake.
5. Raise the plate to a height such that the lift plate is just above the rails of the slot you are installing it
in. Release pins on the lift plate and fully extend the center portion of the plate toward the frame and
lock it in place. Release the pins on the extender arms and position them on both left and right side.
Arms must fit around the frame extenders and lock in place (do not adjust the lift tool after these
arms are locked in place).
6. One person should gently push the IBF into the frame. Adjust the height of the lift plate, as needed.
7. Lower the lift plate and remove it from the lift tool, repackage the lift tool.
8. Fasten the IBF to the mounting rails, using two mounting bolts.
9. Ensure the circuit breaker is in the off (right) position if it is not already off.
10. Plug the battery cable into the IBF. Fasten the cable-retaining clamp (closest to the cable's connector)
to the frame, using a 7-mm M5 screw
11. Reinstall all components removed during the removal process.
12. Set the circuit breaker to the on (left) position.
13. Press the white Service Complete button on the UEPO switch to indicate completion of this
procedure.