140 NT5D97 Dual-port DTI2/PRI2 installation and removal
9
10
11
12
13
14
15

Remove the NT5D97 DDP2

Use
141)
Copyright © 2003-2007, Nortel Networks
.
CAUTION
Clock Controller cables connecting the Clock Controller
and NT5D97 card must NOT be routed through the center
of the cabinet past the power harness. Instead they should
be routed around the outside of the equipment shelves.
If required, install connecting blocks at the MDF or wall mounted
crossconnect terminal.
If required, designate connecting blocks at the MDF or wall mounted
crossconnect terminal.
If required, install a Network Channel Terminating Equipment
(NCTE). or Line Terminating Unit (LTU).
Add related office data into switch memory.
Enable faceplate switch S1. This is the "Loop Enable" switch.
The faceplate LEDs should go on for 4 seconds then go off and
the OOS, DIS and ACT LEDs should go on again and stay on.
IF DDCH is installed, the DCH LED should flash 3 times.
Run the PRI/DTI Verification Test.
Run the PRI status check.
Procedure 15 "Remove the NT5D97 from Large Systems" (page
to remove the NT5D97 from Large Systems
CAUTION
The static discharge bracelet located inside the cabinet must be
worn before handling circuit cards. Failure to wear the bracelet
can result in damage to the circuit cards.
Nortel Communication Server 1000
ISDN Primary Rate Interface Installation and Commissioning
NN43001-301 02.03 Standard
Release 5.5 7 December 2007
—End—