Commissioning
5.1
Commissioning ET 200eco PN
Introduction
Your automation system is commissioned depending on the current plant configuration. The
section below describes the procedure for commissioning the ET 200eco PN on an IO
Controller.
Requirements for commissioning the ET 200eco PN on the PROFINET IO
Actions
ET 200eco PN installed
ET 200eco PN wired
The IO Device was assigned a device name
ET 200eco PN configured
Supply voltage for the IO Controller is switched on
IO Controller switched to RUN
Commissioning ET 200eco PN
1. Switch on the voltage supply 1L+ non-switched for the ET 200eco PN.
2. Switch on the supply voltage(s) 2L+ switched as required.