iSitePower-M (MAP05A1, MAB05B1)
User Manual
11.1 System Power-On
● The product must be powered on within 24 hours after being unpacked. During
● If an alarm is generated on the app before the system is powered on, you need
● Before upgrading the ESS, ensure that no short circuit occurs on load cables. A
● If there is no AC input or PV input, you need to manually start the system by
● In a parallel system, after cables are connected, disconnect loads first. Start all
● When the output voltage system is adjusted, the equipment is powered off and
● If there is no AC input, the product will be powered off during the upgrade.
Procedure
Step 1 Turn on the corresponding switches based on the scenario.
●
●
Step 2 Set the AC input circuit breaker of the iSitePower-M to ON.
Step 3 After the initial installation and power-on, observe the LED indicator to check the
running status.
----End
11.2 System Commissioning
11.2.1 Installing the App
Prerequisites
A mobile phone running Android 8.0 or later is available.
Downloading and Installing the FusionSolar App
●
Issue 06 (2023-04-24)
NO TICE
maintenance, the power-off time cannot exceed 24 hours.
to manually clear the alarm on the app.
short circuit may damage the ESS.
pressing the manual ON/OFF switch.
slave products and then the master product. After all products are started, log
in to the master product to set parameters.
then restarted. No manual operation is required.
Therefore, you are advised to upgrade the product when AC input is available.
If there is PV input, hold down the manual ON/OFF switch for 5s, and turn on
the DC SWITCH.
If there is no PV or AC input, hold down the manual ON/OFF switch for 5s.
Method 1: Access https://solar.huawei.com using the mobile phone browser
and download the latest installation package.
Copyright © Huawei Digital Power Technologies Co., Ltd.
11 System Commissioning