10.7.3 Installing Output Power Cables for the AC Parallel Box

● The live (L) wire and neutral (N) wire of an AC power cable must be correctly
● The PE wire of an AC power cable must be grounded.
● Do not reversely connect AC output power cables.
● Install short-circuit plates for AC output circuit breakers.
● The three cables from the AC output circuit breaker to the power modules must
Procedure
Step 1 Install AC output power cables for the parallel box.
Issue 06 (2023-04-24)
CA UTION
connected.
NO TICE
be of the same length.