11. Install the following, as needed:
Expansion boards (Installing an expansion board in the primary riser cage on page 87)
Controllers (Controller options on page 100)
12. Install the primary PCI riser cage (Install the primary PCI riser cage on page 35).
13. Install the access panel (Install the access panel on page 32).
14. Install the server in the rack.

Installing an expansion board in the primary riser cage

Prerequisites
Before installing this option, be sure you have the following:
The components included with the hardware option kit
T-10 Torx screwdriver
Procedure
1.
Observe the following alerts:
WARNING: To reduce the risk of personal injury from hot surfaces, allow the drives and the internal system
components to cool before touching them.
CAUTION: To prevent damage to electrical components, properly ground the server before beginning any
installation procedure. Improper grounding can cause electrostatic discharge.
2.
Back up all server data.
3.
Power down the server (Power down the server on page 31).
4.
Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
5.
Do one of the following:
a. Extend the server from the rack (Extend the server from the rack on page 31).
b. Remove the server from the rack (Remove the server from the rack on page 32).
6.
Remove the access panel (Remove the access panel on page 32).
7.
Remove the primary PCI riser cage (Remove the primary PCI riser cage on page 34).
8.
Remove the expansion slot blank.
Hardware options installation