5.7.1

Inserting the ground anchorage

NOTE
The design of the ground anchorage must be adapted to the subsoil condition and/or special local
conditions.
The following description of the assembly is therefore only exemplary. Local conditions are not dealt
with in detail. Deviating procedures may only be initiated by competent persons.
Installation requirements
Ground condition with sufficient load-bearing capacity and evenness.
At least 600 mm free space around the charging system for heat dissipation.
Laid supply line
Installation material and tools
Depending on ground conditions, 4 suitable ground anchors (e.g. expansion or injection anchors)
with threaded bolt M10 or internal thread M10 (not in scope of delivery)
Suitable drilling tool
1
Fig. 10: Supply line routing
Carrying out installation
1.
Lay the pillar flat on the ground as close as possible to the installation location.
2.
Guide prepared supply lines through the ground opening (1) of the base into the pillar and push
them through the standpipe (2) to the upper opening.
3.
Pull the supply lines out of the upper opening as far as necessary.