5.6 Mounting on pillar with SMC base

NOTE
The pillar for the compleo Solo charging system is available either with 1 mounting plate (single-sided
pillar) or with 2 mounting plates (double-sided pillar).
Due to the design similarities of the base plate and the standpipe, only the one-sided pillar is used in
the illustration of the following installation instructions. All assembly steps for installation are also
applicable for the double-sided pillar.
Installation sequence
1.
Select a suitable installation site.
2.
Check ground for stability.
3.
Check parts and installation material for completeness.
4.
Excavation of the installation pit.
5.
Lay the supply lines
6.
Compact and level the ground of the excavation pit.
7.
Place and align the SMC base.
8.
Feed the supply lines through the centre of the base.
9.
Fix the base by filling.
10.
Feed the supply line through the pillar.
11.
Place the pillar on the base and screw it down.
12.
Fasten the charging system with installation material.
13.
Prepare electrical installation.
Fig. 5: Pillar on SMC base
1) = The design and number of supply lines depends on the number and equipment of the compleo
Solo charging system to be installed. See chapter 3.3 Technical specifications, page 16.
28
1)
.
A01Axxxxxx.xx | 04
The SMS base is installed exclusively in soil with
sufficient load-bearing capacity and soil
condition.
In case of doubt, a qualified civil engineering
company must prepare the ground and carry out
the installation.
The charging system is then mounted using the
fixing material included in the scope of delivery
and finally installed.
The exact dimensions and weights of the charging
system and the pillar can be found in the
corresponding documents in chapter 13 Annexes,
page 100.
2022-11