Figure 75: Tightening The Handle Locking Screw - Allied Telesis SwitchBlade x908 GEN2 Installation Manual

Stand-alone switches
Hide thumbs Also See for SwitchBlade x908 GEN2:
Table of Contents

Advertisement

Chapter 4: Powering On the Chassis
110
Figure 75. Tightening the Handle Locking Screw
10. Before attaching the power wires from the power supply to the circuit
breaker in the wiring closet, check that the circuit breaker is off.
11. Connect the power wires to the circuit breaker.
12. If you have two SBxPWRSYS1-80 DC Power Supplies for the switch,
repeat this procedure to install the second power supply.
13. Turn the DC circuit breaker(s) on.
14. Turn the On/Off switch(es) on the SBxPWRSYS1-80 DC Power
Supply(ies) to the On position. See Figure 60 on page 97.
15. Do one of the following:
To monitor the switch as it initializes the management software, go
to "Monitoring the Initialization Processes" on page 121.
Wait three minutes for the switch to initialize its management
software. Afterwards, go to Chapter 5, "Verifying the Hardware
Operations" on page 125.