19 Setup Outline

19.2 Flow of Initial Setup

The following flow chart shows the procedures of the initial setup.
(Note)
When setting up with backup files, refer to the chapter of "Data Backup and Restoration".
WARNING
Do not cancel the emergency stop before confirming the basic operation.
Confirming the connection between
control unit and peripheral devices
Setting the Hardware
Setting Up with
HMI Integrated Installer
Setting the machine parameters (1)
Formatting the NC memory
Setting the machine parameters (2)
Setting Date and Time
Sequence Program Writing
Confirming the Basic Operation
Setting the Position Detection System
Setting the Stored Stroke Limit
Setting the Machine Error Compensation
Setting the Position Switches
Setting the Backash Compensation
Confirming the Spindle Operation
Setting the Handy Terminal
Inputting the machining program
Start
Points
Is the power supply within a specified range?
Is the power supply polarity correct?
Is the connection of the motor power cable and the encoder cable correct?
Is the grounding correct?
Refer to section 20
Carry out the connecting and setting of drive units, batteries and remote I/O units.
Initialize the NC Internal data (SRAM).
Refer to section 21
Install and upgrade "Application of custom release"
with the HMI integrated installer.
If you do not need the installation, go to the next section.
Refer to section 22.1 to 22.2
Selecting the NC system type and displayed language.
Setting the parameters for the system specifications.
Refer to section 22.2
Refer to section 22.3
Setting the parameters for the machine specifications.
Refer to section 22.4
Set the date and time on the integrated time screen.
Refer to section 23
Write the created sequence program to NC's ROM using GX Developer or GX Works2.
Refer to section 24
Confirm input/output of signals, alarm display and manual operation.
Refer to section 25
Carry out the setting for establishing the reference position (zero point).
Refer to section 26
Set the tool entry prohibited range.
Refer to section 27
Set the memory-type pitch error compensation, the memory-type relative position error
compensation, and the bidirectional pitch error compensation.
Refer to section 28
Set the position switches.
Refer to section 29
Set the backlash compensation and the backlash compensation II.
Refer to section 30
Confirm that the spindle operates properly in manual/MDI operation.
Confirm the spindle rotation speed as well.
Refer to section 31
Input the customized data for the handy terminal.
(Note) This procedure is required only when connecting the handy terminal.
Refer to the Instruction Manual
End