5. Checking the E guide height
(1) Clean the gate base (35) assembly.
(Refer to Section 3-2-1.)
(2) Set the E guide height gauge to the gate base (35)
assembly as shown in the figure.
n
Be very careful not to scratch the surface of the gate
base (35) assembly.
Gate base (35) assembly
(3) Press the E guide height gauge toward the film guide
pin (B)s of S side and T side shown in the figure.
(4) Check the clearances are not existed between the E
guide height gauge and S side film guide pin (B) and T
side film guide pin (B).
If the clearance is existed, perform the E guide height
adjustment according to step 6 and later.
E guide hight gauge
Film guide pin (B) (S side)
E guide hight gauge
Film guide pin (B) (T side)
FVS-1000 MMP1
E guide hight gauge
Check this clearance
Check this clearance
3-4. Replacement of Periodic Replacement Part
(5) While keeping the state of step (3), check the clearance
between the E guide flange and E guide stay 35 using
the thickness gauge. (Check both T side and S side.)
Specifications:
For gate base (35) assembly: less than 0.03 mm
For gate base (16) assembly: There is no clearance.
If not to meet the specifications, perform the E guide
height adjustment according to step 6 and later.
E guide flange
E guide stay 35
Thickness guide