Figure 2-3 Component layout in the IT cabinet to the left of the Converged Cabinet
You are advised to number cabinets and PDU2000s based on
Figure 2-4 Number example
Issue 10 (2019-12-20)
The following describes how to number cabinets and PDU2000s in a scenario with five cabinets.
(1), (2), and (3) refer to the cabinet number, and A and B refer to the PDU2000 number.
You are advised to number cabinets from left to right.
The battery cabinet and Converged Cabinet do not have to be numbered.
PDU2000s are deployed at the cabinet rear door and are recommended to be numbered from exterior
to interior.