Installation Guide (Six Fans)
Table 6-6 Commissioning the sensor
Check Method
Simulate a smoky
environment under
the smoke detector.
----End

6.3.6.2 Commissioning the Water Sensor

Procedure
Step 1 Set water sensor parameters.
1.
2.
3.
4.
5.
6.
7.
Step 2 Check the monitoring functions of water sensor.
Table 6-7 Commissioning the sensor
Check Method
Place the water detection cable
into water.
----End

6.3.6.3 Commissioning the Temperature Sensor

In the scenario with an emergency fan, perform this operation by default when the
temperature sensor is configured and connected to the AI/DI_2 port.
Issue 10 (2019-12-20)
Normal Connection Status
Smoke DI alarm is displayed on
the active alarm page of the app
or WebUI.
The parameter has been preset before delivery.
In this example, the water sensor is connected to the AI/DI_1 port on the ECC800.
Log in to the ECC800 WebUI as an administrator.
Choose System Settings > Signal Name Modify. The Batch Signal Configuration
page is displayed.
Set Device type to ECC800, set Device name to ECC800, and click OK.
On the query result tab page, set the new signal name of AI/DI_1 to Leak and click
Submit.
Choose Monitoring > System > ECC800 > Running Parameters > AI/DI_1 Port
Settings.
Set Leak sensor to Enable and click Submit.
Confirm that Leak sensor type is automatically identified as Leak sensor(Rope).
Ensure that Leak power supply is Yes.
Copyright © Huawei Technologies Co., Ltd.
Alarm Clearance Method
Press the reset button of the
smoke sensor to clear the alarm.
Normal Connection Status
Leak DI alarm is displayed on the active alarm page
of the app or WebUI.