Management System Power-On Commissioning; Preparations And Webui Login - Huawei FusionModule800 Installation Manual

Smart small data center six fans
Hide thumbs Also See for FusionModule800:
Table of Contents

Advertisement

FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
Table 6-3 Set UPS parameters
Parameter
Batteries (10 kVA
UPS)
Positive
batteries/Negative
batteries (20 kVA
UPS)
Battery capacity
Note: use two UPSs sharing a 65 Ah battery string as an example: if the calculated battery
capacity is (65 x 1)/2 = 32.5, set it to 32 Ah.
Step 6 Turn on the UPS output switch after the UPS starts.
Step 7 Switch on the PDU2000 circuit breakers one by one on the PDU and switch on the PDU2000
circuit breaker in the rear of the cabinet to power on corresponding devices.
When switching on the circuit breakers, observe whether there is any abnormal phenomenon,
such as sparks.
Step 8 Switch on the ECC circuit breaker on the PDU to power on the ECC.
Step 9 Switch on the smart cooling product circuit breaker on the PDU to power on the smart cooling
product.
----End

6.3 Management System Power-On Commissioning

6.3.1 Preparations and WebUI Login

Prerequisites
User rights:
Issue 10 (2019-12-20)
Default Value
20
65 Ah
For details about how to operate the UPS, see the manual delivered with the UPS.
The default user with administrator rights is admin. The preset password is Changeme.
The admin user has all WebUI operation rights.
Copyright © Huawei Technologies Co., Ltd.
Setting Value
Set as required.
Battery capacity = Capacity of a single battery
string x Number of parallel battery
strings/Number of parallel UPSs sharing a battery
string.
6 Power-On Commissioning
235