FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
Name, Specifications, and Appearance
temperatures higher than 85° C and the following requirements are met:

2.2 Checking the Installation Environment

Ensure that the installation environment meets the requirements before installation.
Table 2-3 Installation environment checklist
Check Item
Bearing capacity
Levelness
Equipment room
height
Equipment room
area
Door size
Elevator
Power supply
Lighting
Issue 10 (2019-12-20)
Applicable to all pipe materials
Anaerobic metal pipe thread sealant with PTEF as the padding
Maximum gap: 0.5 mm
Pressure resistance: above 1.6 MPa
Compliant with the industry standard JB∕T7311-2008 Technical Specification for the
Application of Anaerobic Glue in Engineering Machinery
Specifications
Allowed deviation: 3/2000 mm
≥ 2.6 m
8-30 m
Height > 2.2 m; width > 0.9 m
Elevator bearing capacity > 1.5 t
Elevator internal size: height > 2.4 m,
depth > 1.4 m
Elevator door size: height > 2.2 m; width >
0.9 m
380 V AC/400 V AC/415 V AC, 3 Ph, 50
Hz/60 Hz
Copyright © Huawei Technologies Co., Ltd.
Standard live load of the main
equipment room: 8-12 kN/m
battery cabinet is placed inside the
module, use the standard live load of the
main equipment room as a reference.)
Suspended load of the main equipment
2
room: 1.2 kN/m
Standard live load of the battery room:
2
16 kN/m
2
Equipment room: 500 lx
Monitoring center: 500 lx
2 Installation Preparations
Check Result
□ Passed □ Failed
2
(If the
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
17

Advertisement

Table of Contents
loading

Table of Contents