FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
No.
10
Cable Installation Check
Table 5-5 Cable installation check items
No.
1
2
3
4
5
6
7
8
Electrical Installation Check
Table 5-6 Electric installation check items
No.
1
2
3
4
Issue 10 (2019-12-20)
Check That
is left onsite.
Block empty cable holes using plugs or lids.
Check That
All cable joints are secured properly, especially the cable
joints between network cables.
Exposed parts near the wiring terminals and lugs are
wrapped in PVC insulation tape or heat shrinking tubing.
The flat washers and spring washers of all wiring
terminals are securely installed.
Cables are bound neatly and cable ties are secured evenly
and properly.
Routed cables should be convenient for future
maintenance and expansion.
All labels at the cable ends are clear.
The excess section of a cable strip is cut evenly.
There are no unnecessary adhesive tape or cable ties on
cables.
Check That
All ground cables are copper cables. Cable diameters are
correct. No switches or fuses are installed on the cables
and no short circuit occurs.
The ground cable, AC power cables, and internal cables
are correctly connected and screws are secured. No short
circuit occurs during power input or output.
The smart cooling product input voltage is within the
range of rated voltage ± 10%, and the input frequency is
within the range of rated frequency ± 3 Hz.
The length of ground cables and power cables is correct.
Copyright © Huawei Technologies Co., Ltd.
5 Checking After Installation
Check Result
□ Passed □ Failed
Check Result
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
Check Result
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
230

Advertisement

Table of Contents
loading

Table of Contents