FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
If two smart ETH gateways are configured, install them in positions shown in
3-186.
If three smart ETH gateways are configured, install two of them in positions shown in
Figure
cabinet.
(1) Smart ETH gateway
Issue 10 (2019-12-20)
3-186, and install the remaining one on the M-shaped cable trough of an adjacent
Figure 3-186 Position 1 for installing a smart ETH gateway
If M-shaped cable troughs are not deployed for the Smart Module, install the smart ETH
gateway on the top of the Converged Cabinet, as shown in
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation
Figure
Figure
3-187.