Figure 43. Insert the Power/Alarm Connector
14. On the AT-IS230-10GP switch, tighten the two connector fastening
screws on the ends of the power/alarm connector to the chassis as
shown in Figure 44.
Figure 44. Fasten the Power/Alarm Connector to Chassis
15. After inserting and fastening the power/alarm connector, go to "Apply
Power To Switch" on page 86.
IS Series Industrial Ethernet Layer 2 Switch Installation Guide