2. Commissioning
2.5
Check list for commissioning the CPX terminal with FB32
2-40
•
Please observe the general commissioning instructions in
the CPX system description.
•
Check the DIL switch settings and the network
configuration before using and replacing CPX terminals.
•
Check the configured address range. If necessary,
test the I/Os.
•
Check the address assignment of the I/Os on the CPX
terminal. For this purpose you can, if necessary,
force the I/Os (see CPX system description).
•
Make sure that the desired parameterisation of the CPX
terminal in the start-up phase or after fieldbus
interruptions is restored by the plug-in module.
This is to ensure that if the CPX terminal is replaced, the
new terminal will also be operated with the desired
parameter settings.
•
Use spot checks if necessary to check the
parameterisation, e.g. with the configuration program or
with the Handheld.
Festo P.BE-CPX-FB32-EN en 1111a