Testing the complete configuration
Testing the complete configuration
This section provides tests for the complete configuration, including the control and signaling networks
and the telephones and consoles.
This section provides tests to:
•
review the status of the configuration.
•
test the IP server interfaces, expansion interfaces, and TDM buses in the port networks.
•
test the telephones and other equipment.
See
LED indicators
servers, Avaya Ethernet switch(es), uninterruptible power supplies (UPSs), and different circuit packs.
Perform these tasks to test the configuration:
•
1
2
3
4
5
6
7
8
Testing port network equipment
These tests verify that the time division multiplexing (TDM) cables and terminators work. If a FAIL
Result code is seen, check these cables. If problems persist, see the maintenance book for your
configuration .
298
on page 309 for information regarding the LED status indicators for the media
NOTE:
Circuit pack positions are usually given by cabinet, and slot. They may also be given by
port. The term "cabinet" refers to five G650 Media Gateway TDM-cabled together in a
rack, making up one port network. A port network is defined as a group of media
gateways connected together with one TDM bus.
CAUTION:
To prevent unnecessary trouble tickets, do not enable the alarms (Alarm Origination
feature) until all installation and administration procedures are completed.
Testing the license file
on page 301
Testing telephones and other equipment
Installing the Avaya S8500 Media Server with an Avaya G650 Media Gateway
on page 305