Installing and administering the patch
cord/jumper
Before starting the patch cord installation, obtain a copy of the Port Assignment Record forms from the
customer or marketing representative. See
The white label identifying the terminal block row associated with circuits 17 to 24 connects to an
identically labeled terminal block row at the satellite closet. See
information outlet,
The satellite symbol must be installed at all connection points between the blue field and the information
outlet. It must also be installed at the information outlet itself.
Figure 81, Example 4-pair labeling to information outlet,
for 4-pair circuits from the equipment room to the information outlets. The labeling scheme for 3-pair
circuits from the MDF to a satellite location.
210
on page 211. This is always the case for either 1-point or 2-point administration.
Installing the Avaya S8500 Media Server with an Avaya G650 Media Gateway
Port Assignment Record Form
Figure 80, Example 3-pair labeling to
on page 212 shows an example labeling scheme
on page 203.