2-16
AP-7131N-FGR Access Point Product Reference Guide
NOTE The AP-7131N-FGR is Plenum rated to UL2043 and NEC1999 to support
CAUTION Motorola does not recommend mounting the access point directly to
!
The mounting hardware required to install the access point above a ceiling consists of:
• Light pipe
• Badge for light pipe
• Decal for badge
• Safety wire (strongly recommended)
• Security cable (optional)
To install the access point above a ceiling:
1. If possible, remove the adjacent ceiling tile from its frame and place it aside.
2. Install a safety wire, between 1.5mm (.06in.) and 2.5mm (.10in.) in diameter, in the ceiling
space.
3. If required, install and attach a security cable to the access point's lock port.
4. Mark a point on the finished side of the tile where the light pipe is to be located.
5. Create a light pipe path hole in the target position on the ceiling tile.
6. Use a drill to make a hole in the tile the approximate size of the LED light pipe.
CAUTION Motorola recommends care be taken not to damage the finished
!
7. Remove the light pipe's rubber stopper before installing the light pipe.
above the ceiling installations.
any suspended ceiling tile with a thickness less than 12.7mm (0.5in.)
or a suspended ceiling tile with an unsupported span greater than
660mm (26in.). Motorola strongly recommends fitting the access point
with a safety wire suitable for supporting the weight of the device.
The safety wire should be a standard ceiling suspension cable or
equivalent steel wire between 1.59mm (.062in.) and 2.5mm (.10in.) in
diameter.
surface of the ceiling tile when creating the light pipe hole and
installing the light pipe.