OPERATION TEST

Confirm the entered system data and hardware, including cable connection, by completing the following
operational tests.
• Basic Connection Test at MDF
Station Line Test (Operator Call from all stations)
Central Office Trunk Test (Incoming, Outgoing)
Tie Line Trunk Test (Incoming, Outgoing)
• Service Feature Test
Call Transfer
Step Call
Executive Right of Way (Executive Override)
Call Hold
Call Back
Call Forwarding-All Calls/Don't Answer (No Answer)/Busy Line
Call Pickup
Station Hunting-Pilot/Circular
Speed Calling-Station/System (Station Speed Dialing/System Speed Dialing)
Paging Access (External Paging with Meet-me)
Announcement Service
Other selected features
NOTE:
Feature names in the parenthesis are for North America.