CHAPTER 2 INSTALLATION
INSTALLATION OF MAIN EQUIPMENT
• Installation of TOP COVER
(1) Hang four hooks of the TOP COVER on the back board of PIM as shown below.
(2) Secure the TOP COVER to the front side of the PIM with two screws.
NOTE:
Screws are attached to BASE/TOP ASSEM.
HOOK
– 98 –
NWA-008841-001 Rev.5.0