Commissioning
5.1
Commissioning guidelines
Overview
SINAMICS G120C Converters
Operating Instructions, 02/2023, FW V4.7 SP14, A5E34263257B AK
1. Define the requirements to be met by the
drive for your application.
(Page 121)
2. Restore the factory settings of the con‐
verter if necessary.
(Page 153)
3. Check if the factory setting of the con‐
verter is sufficient for your application.
(Page 122)
4. Set the following for quick commission‐
ing of the drive:
– The closed-loop motor control
– The inputs and outputs
– The fieldbus interface
(Page 124)
5. Check if additional converter functions
are required for the application.
(Page 183)
6. If necessary, adapt the drive.
(Page 183)
7. Save your settings.
(Page 165)