Foundation Work - Doosan HM 1000 Installation Manual

Hide thumbs Also See for HM 1000:
Table of Contents

Advertisement

HM 1000/1250

1.2 Foundation Work

1) Foundation work timing and post checkpoints
① It is recommended to take a two-month schedule from completion of the foundation
work to completion of the installation.
▪ It should take at least one month to cure the concreted surface.
② After completion of the foundation work, measure each checkpoint on the foundation
and take an appropriate action (mostly repair) if a problem is found.
2) Foundation work for installing the machine
① Foundation Diagram
6
HM1000ISE99
※ Note)
1) Models applicable
▪ HM1000
▪ 2100(X) × 1250(Z)
▪ ATC : 60 Tool
▪ APC : ST2100
2) Tolerance for each checkpoint
▪ Top view: ±10mm
▪ Gap between holes: ±10mm
▪ Cumulative gaps between holes :
±20mm
▪ Size of foundation hole: ±10mm
3) Theoretical requirements of foundation
material
▪ First concrete: 16.1m³
▪ Second grout: 1.1m³
4) This diagram is a standard machine
layout for reference. The actual layout
may differ depending on the machine.
Refer to the layout diagram that is
specific to the machine to install.