6. Assembling the main unit
6.1 Installing the duct
1) Locate the cable duct in the shipping package
and put it back to the original position.
Position: under the electric cabinet from the X-
axis bed.
2) Install the X-axis bed duct on the side of the X-
axis bed.
6.2 Connecting wires and hydraulic hoses
Untie the provided wires and hydraulic hoses and put them in order so that you can
connect them in the their respective position correctly. To facilitate the later process,
arrange and put aside the wires and hoses that are to be connected after the precision
machining and installation of the splash guard.
1) Connecting the hydraulic hoses from the table bed
Connect the hydraulic hoses arranged in the table bed to the connectors of the manifold
attached to the column bed while checking the tags one by one.