10) When TMG pan and guard are installed
properly, proceed with TMG skirt.
14. Installing the coolant tank & chip conveyor

14.1 Installing the coolant tank

1) Arrange the wires and hoses through the duct
of the coolant tank and push in the coolant tank
(with the chip conveyor installed) in the right
position.
▪ Fit the screw conveyor into the coolant tank
holes and push it in until the conveyor contacts
on the bed.
2) Connect the wire connectors from the electric
cabinet and wire connectors from the chip
conveyor to the terminal box on the coolant
tank.
102
Pan Support
Electric
Cabinet
Connector
Chip
Conveyor
Connector