Curing The Surface Of Mortar - Doosan HM 1000 Installation Manual

Hide thumbs Also See for HM 1000:
Table of Contents

Advertisement

HM 1000/1250
Injecting grout in APC
2) Grout Compacting
Use a pipe or long thin pole to keep stirring in the grout mixture so that the mixture fills
up the whole hole evenly without the buildup of air bubbles.
▪ Do not use the vibrator specific to concrete compacting while injecting grout.
3) Clean up the floor when the hole is filled up
with grout.

5.5 Curing the surface of mortar

1) Keep supplying an adequate amount of water on the surface in the course of grout
curing.
▪ It is recommended that the surface be covered with a wet cloth to slow down moisture
evaporation.
2) Make a generous schedule for the grout curing.
▪ The longer the curing period is, the greater the strength. Assign at least 5 days for
grout curing (7 days is recommended). Allow additional 2 or 3 days for the curing in the
wintertime.
3) Keep vibrations, shocks and loads to a minimum level and maintain the ambient
temperature above 10˚C for the curing period.
▪ When it is too low in temperature in the winter season, use a heater or hot blast stove
to maintain an appropriate temperature.
HM1000ISE99