4.4 Temporary Installation of APC

1) Install the foundation components onto APC in the same manner as you did onto the
bed.
Stud Bolt
Plain
Washer
Level-bolt
Fixing Nut
Level Block
2) Install the APC temporary bracket in the X-axis bed and place APC over APC temporary
block.
APC Temporary
Bracket
3) Remove the rear cover of APC (top of the motor), and place a long block in the X-axis
direction (i.e., Z-axis direction in the APC guide way). Then, place the level on the block
and install APC temporarily.
① Strike a horizontal balance while checking the level.
② Align the height and distance while checking the position of the APC temporary front
bracket.
③ Adjust the overall parallelism while eye-checking the installation line in the X-axis
bed.
4) When the temporary installation of APC #1 is completed, repeat the same process for
APC #2. Install the APC temporary rear bracket to adjust the distance between two
APCs.
Block
22
Nut
Bush
Level
Bolt
Anchor
APC Temporary
Rear Bracket
HM1000ISE99
APC Temporary
Block
APC Temporary
Front Bracket