9.12

Initial Operation Setting Function

This function sets whether the initial processing using the program is necessary or not when the data link is
established. The function enables the I/O module to operate (enabling the update of external I/O) with the program for
initial processing not being set.
(1) Applicable module and software
The initial operation setting function cannot be used depending on the combination of the I/O module and
software package used. For details, refer to the following.
Module
NZ2GF2B1-16D
NZ2GFCE3-16D
NZ2GFCE3-16DE
NZ2GFCM1-16D
NZ2GFCM1-16DE
NZ2GF2B1-16T
NZ2GF2B1-16TE
NZ2GFCE3-16T
NZ2GFCE3-16TE
NZ2GFCM1-16T
NZ2GFCM1-16TE
NZ2GF2B1N-16D
NZ2GF2B1N-16T
NZ2GF2B1N-16TE
(2) Operations of when the initial operation setting function is used
The operations of when the initial operation setting function is used vary depending on the setting value of "Initial
operation setting". Note that "Initial operation setting" cannot be set to "1: Without initial processing" for the I/O
module with a serial number (first five digits) of "16041" or earlier. This module operates only with "0: With initial
processing" being set. Also, when setting parameters using Initial processing request flag (RWr0.b8) as an
interlock as shown in the program example, set "Initial operation setting" to "0: With initial processing".
For program examples of initial processing, refer to the following.
• Initial processing ( Page 222, Section 10.3 (6) (a))
Serial number (first five digits)
"16042" or later
Version 1.513K or later
"16111" or later
CHAPTER 9 FUNCTIONS
Version of GX Works2
Version of GX Works3
Version 1.000A or later