Connect The Interlock Cable - ABB HVC Installation Manual

450 kw e-bus charger
Table of Contents

Advertisement

HVC 450 kW E-Bus Charger Installation Guide
A
Terminal block
B
AC utility power cable
1.
Move the cable towards the terminal block (A).
2.
Strip 0.43 Inch of the insulation from the ends of the wires.
3.
Crimp a ferrule onto the end of the wire.
4.
Loosen the connector screws.
5.
Insert the wires into the connectors, see table below:
Functional description
GND
L1
L2
L3
6.
Tighten the connector screws.

5.8.3. Connect the Interlock cable

Interlock cable connection in the slave 2 HVC 150S:
A
Terminal block
B
Interlock cable from/to slave 1 HVC 150S
1.
Move the cable towards the terminal block (A).
2.
Strip 0.43 Inch of the insulation from the ends of the wires.
3.
Crimp a ferrule onto the end of the wire.
4.
Loosen the connector screws.
5.
Insert the wires into the connectors, see table below:
Functional description
Interlock In (slave 1 HVC 150S)
Interlock Out (slave 1 HVC 150S)
Interlock GND
See also Appendix H Signal connection diagram.
6.
Tighten the connector screws.
Revision: 1.2
Date released: 16-08-2018
Connector
Wire color
X341-1
Green/yellow
X341-2
Black
X341-3
Red
X341-4
Blue
Connector
X286-4
X286-8
X286-9
Wire number
2
1
Shield
COMPANY CONFIDENTIAL
Page 74 of 128