Connect The Can Cable - ABB HVC Installation Manual

450 kw e-bus charger
Table of Contents

Advertisement

HVC 450 kW E-Bus Charger Installation Guide

5.8.4. Connect the CAN cable

CAN cable connection in slave 2 HVC 150S:
A
Terminal block
B
CAN cable to slave 1 HVC 150S
1.
Move the cable towards the terminal block (A).
2.
Strip 0.43 Inch of the insulation from the ends of the wires.
3.
Crimp a ferrule onto the end of the wire.
4.
Loosen the connector screws.
5.
Insert the wires into the connectors, see table below:
Functional description
CAN H Out
CAN L Out
CAN GND
See also Appendix H Signal connection diagram.
6.
Tighten the connector screws.
Revision: 1.2
Date released: 16-08-2018
Connector
X286-10
X286-11
X286-12 or Shield Can Out
Wire color
Brown
White
Shield
COMPANY CONFIDENTIAL
Page 77 of 128

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents