HVC 450 kW E-Bus Charger Installation Guide
1.
Check the delivery goods and boxes for damages.
2.
Check that all cable connections on the pantograph and Wifi communication unit are tight.
Make sure that the painted seal on the pantograph
electrical connectors are not damaged. Is this not the
case, contact ABB Delivery department (see Contact
information on Page 13 for contact details).
5.11.2.

Remove packaging

1.
Remove the packing foil from the frames.
2.
Open the front side of the wooden box with the plate work.
3.
Keep the bag with bolts and nuts to assemble the pole in a safe place.
5.12.

Move the ABB pole to position

Preconditions:
The Charge control set are unloaded from the delivery truck.
The bolts of the foundation are free from dust. If necessary clean the bolts with a
vacuum cleaner or brush.
The work must be carried out by at least two persons.
Make sure that the main switch of the power supply group for the product
is set to the OFF position. Do a voltage check to make sure that the
electrical power is disconnected from the system.
Make sure that personnel cannot be crushed or get stuck while moving
the parts of the Charge control set.
Make sure that personnel cannot be falling from the platform when
working at height.
Warranty
Damage due to moving the Charge control set to its position is not
covered by the warranty.
1.
Lift the vertical frame by using two slings. The slings have to be attached to the top part
of the vertical frame as indicated below. Weight of the vertical frame is 1840.86 lb.
Revision: 1.2
Date released: 16-08-2018
WARNING
DANGER
WARNING
WARNING
CAUTION
COMPANY CONFIDENTIAL
Page 83 of 128

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents