Route The Cables - ABB HVC Installation Manual

450 kw e-bus charger
Table of Contents

Advertisement

HVC 450 kW E-Bus Charger Installation Guide
C7
Connect the GND wire to the ABB Pole on Page 89 and Connect cables ACS Control
Module on Page 91.
C8
Install masks plate work on Page 103 and Grouting of the pole construction on Page
108.

5.2. Route the cables

1.
Unpack the cables. See Cabling on Page 46 for details which cables must be used.
2.
Remove the top cover plate (B) and the front cover plate (C) from the foundation (A) by
loosen the bolts (D).
3.
Put the front cover plate (C) and its bolts (D) in a safe location as it will be installed again
later on.
Step 2 and 3 are only applicable when the Power Cabinet is placed on a
concrete foundation.
The top cover plate is not needed any more after the cabinet is placed on
the foundation.
4.
Route the DC power cables through the 6.30 Inch cable conduit.
5.
Route the AC utility power, GND wire and Interlock cable through the other 6.30 Inch
cable conduit.
6.
Route the communication glass fiber cable through the extra 1.58 Inch cable conduit.
To prevent damage to the glass fiber optic cable, a minimum of two
persons is required to route the glass fiber cable through the conduit. One
person for pulling, the other person to guide the glass fiber cable.
Ensure that the glass fiber cable is carefully rolled out before it is pulled
through the conduit, and do not use large traction forces, this can damage
the glass fiber cable.
Revision: 1.2
Date released: 16-08-2018
NOTICE
CAUTION
COMPANY CONFIDENTIAL
Page 52 of 128

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents