HVC 450 kW E-Bus Charger Installation Guide

4. Construction

4.1. About construction

The construction phase includes all work required to prepare the location and make it ready
for the placement and connection of the HVC 450 kW E-Bus Charger. The construction phase
can start when:
All engineering work is done.
All permits are granted.
The grid connection is available.
The planning steps for the construction phase are shown in the figure below:
B1
Civil engineering works
Construction of the foundation. See section Construct foundation of the Power
Cabinet on Page 36 and section Construct foundation of the ABB Pole on Page
41.
Installation of the cables. See section Cabling on Page 46.
Construction of the bus stop surrounding. See section Geometry of
infrastructure on Page 27.
B2
Electrical engineering works
See section Electrical engineering on Page 33 and section Upgrade grid on Page 26.
B3
Internet access (optional)
This step can be ignored if the location has sufficient 3G coverage. Otherwise an
Ethernet (RJ45) connection has to be installed. See section Internet connection on
Page 50.